The blog you see is the real installation site of the clean room project carried out by Suzhou Pharma Machinery in Africa. A lot of people are wondering how to install wall panels especially long sandwich panels?
The blog you see is the real installation site of the clean room project carried out by Suzhou Pharma Machinery in Africa. A lot of people are wondering how to install wall panels especially long sandwich panels in the video?
First of all, transport the panel to the wall, pay attention to avoid bumping; Place the panel flat on the ground, lift one end up on the lifting platform, and place the other end in the corner aluminum that is fixed in advance.
Then slowly raise the lifting platform until the panel also stands up with the lifting platform and leans against the wall; Adjust the height and position of the lifting platform to facilitate operation and ensure worker safety.
Finally inserting the bottom of the panel in the ground trough aluminum, and then aligning two panels and tight them . The top joint of the two panels can be fixed by short groove aluminum.
Use this method until the entire wall installation is complete. In this way, the installation of long walls can be completed quickly and safely

Since its inception, Suzhou Pharma Machinery has successfully completed hundreds of purification engineering projects; From design, production to installation and commissioning, we provide customers with comprehensive, professional and customized services. Professional designers, engineers, sales staff are dedicated to provide customers with the best quality service. Through these successful cases, we have not only accumulated valuable experience, but also established a long-term trust relationship with our customers. We warmly welcome your message to negotiate business.