Precautions For Installation Of Cleanroom Color Steel Panels

Familiarize yourself with the cleanroom drawings, and carefully review the following details: layout of color steel panels, joint requirements, connection between color steel panels and the building structure, color, filler, and basic dimensions of the color steel panels themselves, dimensions and layout of doors and windows in color steel panel partitions, type of auxiliary materials, and other unclear contents.

Secondary panel layout drawing: This is a crucial step in the prefabrication and installation of color steel panels. It is an intermediate conversion drawing that transforms the design drawings into a format suitable for secondary processing in the factory-converting standard-sized panels into different types of wall panels for assembly to realize the design intent. Standard panels are produced in the color steel factory and assembled on-site, which not only ensures the firmness of the wall panels but also speeds up the installation of color steel panels.

During prefabrication in the cleanroom factory, fully consider gaps and installation allowances for door openings, window openings, and joints based on experience. Throughout the transportation, fabrication, and installation process, prevent scratches, heavy pressure, and surface impacts to avoid irreparable dents and scratches. The plastic protective films on both sides of the color steel panels shall only be removed during thorough cleaning after the entire installation is completed.

The setting-out work for color steel panel installation in the cleanroom shall be carried out after the floor (or mezzanine floor) is completed, and shall only start when other relevant installation conditions are met-such as the placement of large equipment in position, the adjustment of concealed floor pipelines, and the substantial completion of main installation work in the technical mezzanine. Setting-out involves marking the horizontal projection (50mm wide) of the color steel panels and the positions of doors and windows on the floor. The centerlines of the upper and lower base channels shall be on the same vertical plane, with a tolerance of no more than 1.0% (i.e., 3mm).

Installation of upper and lower base channels: The lower base channel is generally made of aluminum alloy profiles with internal and external rounded (R) corners. Fix it to the marked lines on the floor using powder-actuated nails, with nail spacing of 1.2–1.5m along straight lines, and nails placed 0.2m away from corners and ends. For channels with water-stop rubber strips, place two rubber strips (Ф2–3) under the channel before nailing, forming a waterproof and sealed barrier after nailing. The upper base channel is a pressed aluminum channel; for rigid ceilings, fix it to the ceiling slab with a powder-actuated nail gun; for flexible ceilings, suspend it under the floor slab using hangers, with the height determined by the net height of the ceiling.

Detailed installation of wall panels: Install prefabricated panel components according to the layout drawing, and lock adjacent wall panels with fixed inserts. It is particularly important to coordinate with the installation of concealed electrical pipelines and junction boxes while assembling the wall panels. The wall panels shall be vertical, and vertical joints shall be tight (smaller gaps are more aesthetically pleasing) and uniform. During operation, temporarily peel off the protective film on the vertical joints for cleaning-do not remove it completely. Clean the debris in the grooves and hardened glue residues; otherwise, it will be difficult to adjust the vertical joints to be uniform and tight even with excessive force.

Installation of cleanroom ceiling panels: The weight of the ceiling panels is supported by the surrounding vertical panels and T-shaped aluminum hangers in the middle. Fix and reinforce the long-side joints with fixed inserts, and fix the short-side joints with T-shaped aluminum and blind rivets (pull rivets) on the connecting plates.

Color steel panel cladding for columns/boxes and installation of internal/external rounded (R) corners: Columns in the clean area shall be clad with 50mm-thick color steel panels, which helps save materials and standardize the use of 50mm internal/external R corners. First, install and secure stainless steel door/window frames in the door/window openings; when installing doors, pay attention to the opening direction, and install window glass. Adjust the opening speed and force of door closers: generally, the door should open quickly in the first half of the stroke and slowly with reduced torque in the second half to minimize closing impact and noise.

Sealant application: In the clean area, apply sealant to all gaps that may affect cleanliness, including:

Joints between color steel panels;

All gaps between R corners and wall/ceiling panels;

Gaps between air conditioning ducts, air outlets, high-efficiency air filters (HEPA), and wall/ceiling panels;

Gaps between protective sleeves of electrical penetrations and the edges of wall/ceiling openings;

Gaps between all switches, sockets, lamps, and the surface of color steel ceiling panels;

Gaps between all process, water supply/drainage, and protective pipelines and their openings;

Gaps between glass and window frames.

Sealant shall be applied uniformly in the cleanroom only after the color steel panel installation is basically completed, the environment is clean, and thorough cleaning and dust removal have been carried out. Otherwise, the sealant joints are prone to contamination and discoloration (turning black). Within 24 hours after sealant application, avoid dust-intensive operations, floor washing with water, or other activities that may affect the curing and adhesion of the sealant.

Key Terminology Notes

Color Steel Panels: Refers to sandwich panels (with core materials like rock wool, polyurethane, or EPS) used in cleanroom construction, providing airtightness and contamination control.

Base Channels (Upper/Lower): Structural aluminum profiles that fix and support wall panels, ensuring vertical alignment.

Rounded (R) Corners: Curved aluminum profiles used at wall-wall, wall-ceiling, or wall-floor junctions to avoid dust accumulation (a critical requirement for cleanroom hygiene).

High-Efficiency Air Filters (HEPA): Standard filters in cleanrooms, removing 99.97% of particles ≥0.3μm, often required at exhaust outlets for hazardous/toxic pharmaceutical processes.

 