Something About Cleanroom Installation

The installation of wall panels should follow the principle of "first down and then up, first inside and then outside". First, the beam and mullion at the bottom of the wall panel are installed on the basis of the wall to ensure that the position of the beam and mullion is accurate and level. Then, the wall board is mounted on the beam and mullion piece by piece to ensure the perpendicularity and flatness of the wall board. In the installation process, special sealant should be used to seal the gap between the wall panels to ensure the air tightness of the wall.

 

The installation of the top panel should follow the principle of "middle first and then both sides". First, the supporting frame is installed on all sides of the plant to ensure that the position of the frame is accurate and level. Then, the roof is mounted on the supporting frame one by one to ensure the flatness and stability of the roof. During the installation process, the gap between the roof should be sealed with a special sealant to ensure the air tightness of the roof.

 

The installation of doors and Windows should follow the principle of "first door frame and then door fan". First of all, install the door frame on the wall to ensure that the position of the door frame is accurate and level. Then, install the door fan on the door frame to ensure that the door door opens and closes smoothly. During the installation process, special sealant should be used to seal the gap between the doors and Windows and the wall to ensure the air tightness of the doors and Windows.

cleanroom installationGMP Clean room